A Constrained Start Date is a rule placed on an Activity that says, “This Activity can start no earlier than [a specific date].” The Activity may start later than the Constrained Start Date, if Logic Ties dictate. However, a Logic Tie (or lack thereof) may never dictate the Activity to start before the Constrained Start Date
Here is how you assign Logic Ties:
Select and click on the Activity to view or edit the Logic of
Click the “Activity Metrics” tab and click the "Logic" button
Click the Grey Calendar button next to the Constrained Start Date field and select the date that the Activity shall start no later than
- Developer's Tip: To remove the Constrained Start Date, simply click the Red Trashcan button next to the Constrained Start Date field