If Start-to-Finish (SF) ties are present in the schedule being imported, for analyses purposes, SmartPM converts SF ties to Start-to-Start (SS) ties with a commensurate negative lag calculation.
If Start-to-Finish (SF) ties are present in the schedule being imported, for analyses purposes, SmartPM converts SF ties to Start-to-Start (SS) ties with a commensurate negative lag calculation.