Activities with No Actual Start Dates that are 0% Progressed John Tuskowski August 09, 2019 16:23 SmartPM does not accept the Actual Start Date of an activity before it has progressed more than 0% Related articles Changes to Actual Start / Actual Finish Dates Activities with No Actual Finish Dates that are 100% Progressed Actual Dates After the Data Date (e.g. Future Actual Dates) Comments 0 comments Please sign in to leave a comment.