% Complete John Tuskowski August 09, 2019 16:40 Updated If the % Complete rolls backward (e.g. from 50% to 20%), SmartPM ignores the roll back and keeps the previously reported % Complete. If an activity with less than 100% complete is given an Actual Finish Date, SmartPM adjusts the % complete to 100%. Comments 0 comments Please sign in to leave a comment.