SmartPM automatically calculates each Project’s Planned vs Actual Percent Completes via four different calculations.
- Planned: The percent complete anticipated in the Baseline on the date of the latest imported Schedule Update
- Actual: The percent complete reported in the latest imported Schedule Update
Overall: The Overall percent complete is a blended calculation which utilizes the following three calculations, prioritizing each in the order listed:
- Cost: SmartPM isolates all activities with cost associations and utilizes their overall Earned Cost Value to generate the Percent Complete calculation
- Resource: SmartPM isolates all activities with Labor or Non-Labor Resources and utilizes their overall Actual Units reported to generate the Percent Complete calculation
- Duration: SmartPM isolates all activities without cost or resource associations and utilizes their overall Duration Complete to generate the Percent Complete calculation
Note: If your schedule is not Cost or Resource loaded, the Percent Complete calculation will be based solely on Durations