The Schedule Delay section indicates the total delay, future recovery, and end date variance from the Baseline to the latest update on the Project.
Critical Path Delay
- This metric indicates how many days of actual critical path delay the project has suffered to date. Supporting this metric is an in-depth delay analysis complete with a delay table and schedule summary that can be reviewed, analyzed and/or drilled down into.
Future Recovery
- The future recovery of a schedule captures the remediation efforts that have been put in place by the scheduler in order to recover time from the delays that have occurred thus far and bring the project completion date back in.
- User Note: Negative days of future recovery indicate that the end date has been pushed out
End Date Variance
- The end date variance of a schedule captures the diversion of the current schedule completion date from the baseline schedule completion date.