Project Dashboard “Corrections” Tab
Click on “Corrections” tab at the top ribbon bar to access the Corrections Tab. All Corrections that have been created will be listed on the main tab.
Create rules for Corrections to select specific schedules to make corrections and apply the corrections to. There are four rule types:
“Revert”: Make changes that should have been made for a prior date. This creates a rule that applies the change and re-runs the delay analysis assuming that the change is in effect.
“Reject”: Allows users to reject changes from a schedule update and re-runs the delay analysis without the change considered. This rule is applied on a go-forward basis for subsequent schedule updates.
“Bulk Change”: Create a change to a large set of activities, by pre-defined or user-defined Filters that are selected. Changes are applied from the schedule that is selected to a go-forward basis for subsequent schedule updates.
“One-off”: Similar to Bulk Change but creates rules for changes to individual activities. Changes are applied from the schedule that is selected to a go-forward basis for subsequent schedule updates.
For additional information, contact your Customer Service representative.